ED's are Open
2024 Public Notice - Website
Updated Masking Policy - Oct. 4
Chesley ED Update - Jan 2023
Annual Report
2023-03-25 Kincardine CT Ribbon Cutting Event
Hospital Advisor Program
previous arrowprevious arrow
next arrownext arrow

SBGHC News

SBGHC Introduces MOLLI Surgical’s New Technology to Improve Breast Cancer Treatment

South Bruce Grey Health Centre (SBGHC) has introduced MOLLI Surgical’s new technology to the organization’s surgical program to improve breast cancer treatment. The wire-free and radiation-free MOLLI® 2 System is used to locate tumors that cannot be felt during surgery. Historically, patients requiring this type of procedure were required to present to Diagnostic Imaging on

Update on Transition of Inpatient Beds at Durham Site

On May 14, South Bruce Grey Health Centre (SBGHC) hosted a community webinar regarding our decision to transition the 10 inpatient beds currently at the Durham hospital site to the Walkerton and Kincardine sites. Thank you to everyone who joined and asked questions. We recognize that many of you have concerns about these plans and

Community Webinar Recording

If you were unable to join the Community Webinar held on May 14th, a recording is available here.

SBGHC to Host Community Webinar on May 14th

South Bruce Grey Health Centre (SBGHC) recently shared the difficult but necessary decision to transition 10 inpatient beds currently at the Durham site to the Walkerton and Kincardine sites effective June 3rd. This is due to a critical shortage of staff, which is anticipated to intensify during the summer season. Relocating these beds allows us

Kincardine Hospital CT Suite Addition

Slide

March 20, 2023
The CT scanner is operational!

Slide

January 2023
The CT suite addition is nearing completion! The CT scanner will be delivered on February 27th, and the targeted date to begin scanning patients is set for March 20th!

Slide

February 27, 2023
The CT scanner has arrived at the Kincardine hospital!

Kincardine CT Suite Addition December 2022
Slide
Slide

September 2022
Throughout September, the structural steel and metal decking were constructed, and exterior stud framing was completed. Work is now underway on roofing and exterior sheathing.

Slide

August 2022
Installation of structural steel is underway.

Slide

July 2022
Construction continues on the CT suite addition at the Kincardine hospital. This month, backfilling was completed and underground services and insulation were installed. The site is now being prepared for sidewalks and subfloor to be poured.

Slide

June 2022
The CT suite addition is starting to take shape! The foundation has been poured, and next up will be backfilling around the foundation and installing the structural steel and metal decking.

Slide

May 2022
The contractor has mobilized, the construction fencing is up and excavation/demo has begun!

Slide
BREAKING GROUND FOR THE KINCARDINE HOSPITAL CT SUITE ADDITION
Slide
previous arrowprevious arrow
next arrownext arrow

Kincardine Hospital Expansion Project

Image showing the different phases of the Kincardine hospital redevelopment project, along with the timing and estimated cost.
2021-04-22_SBGHC-RENDERING_Overlay-01
Slide 2

March 11, 2021

The 1,800-page report was endorsed by SBGHC’s Board of Directors at their regular meeting on March 3rd and has been submitted to the Ministry of Health and Ontario Health.

Slide 2

Updated February 26, 2021

After an extensive review of various CT scanner options for the Kincardine hospital, evaluating the needs of patients and clinical staff, quality of imaging, radiation dose, technology, capital cost and on-going annual operational costs, and consultation with key stakeholders, SBGHC’s Board selected the Edge Plus CT scanner from Siemens in December 2020.

September 25, 2020

The Ministry of Health has provided funding support and approval to South Bruce Grey Health Centre (SBGHC) to advance the Kincardine hospital redevelopment project forward into Stage 2 of the Ministry’s capital planning process.

Slide 2

May 7, 2019

South Bruce Grey Health Centre (SBGHC) has submitted the Stage 1 report for the redevelopment of the Kincardine hospital to the Ministry of Health and Long-Term Care (MOHLTC).

previous arrowprevious arrow
next arrownext arrow
Skip to content